ConstructSim Work Package Server Setup Guide

To Configure the End-To-End Data Run Workflow

To Configure the End-To-End Data Run Workflow for Pipe Non-IFC Task Processing

  1. In the ConstructSim Executive WorkFlow pane, navigate to the Task Processing > Task Generation > STANDARD - Generate Tasks with Unit Rate Adapter - Non IFC PIPE section.
  2. Right-click the Perform Database SQL Query - Setup SPURT before Non IFC Pipe Task Generation managed command and select Properties.
  3. In the Workflow Properties dialog, set the DBLOCATION to point to the SPURT_<ProjectName>.mdb file.
  4. Do the same for the Perform Database SQL Query - Restore SPURT after Non IFC Pipe Task Generation managed command.

To Configure End-To-End Data Run Workflow to Enable Steel Task Processing

  1. Using ConstructSim Executive, open the project workflow (.vem).
  2. From the End-To-End Data Run > Phase 2 - Populate New VCM with Latest Engineering Data > VCM Attributes, right-click the Set Steel Component VCM Attributes node and select Enable Commands.
  3. From the End-To-End Data Run > Phase 2 - Populate New VCM with Latest Engineering Data > Task Processing > Task Generation, right-click the STANDARD - Generate Tasks with Unit Rate Adapter - STEEL - SSURT node and select Enable Commands.

To Configuring End-To-End Data Run Workflow to Enable Equipment Task Processing

  1. From the End-To-End Data Run > Phase 2 - Populate New VCM with Latest Engineering Data > Task Processing > Task Generation > STANDARD - Generate Tasks Using Generic Unit Rates, right-click the STANDARD - Generate Generic Equipment Unit Rates node and select Enable Commands.
  2. From Task Processing > Task Generation > STANDARD - Generate Tasks Using Generic Unit Rates > STANDARD - Generate Generic Equipment Unit Rates, right-click Create Equipment Construction Tasks Using Generic Unit Rates and select Properties. In the Workflow Properties dialog, and set the UNITRATEFILE attribute value to the [ProjectData] - .\UnitRates\ESURT_<ProjectName>.mdb file.